Budget Preparation 

The PI should generate a draft budget using the BGSU PI Budget Template or another appropriate template.   

  • The BGSU PI Budget Template has embedded calculations to facilitate budget preparation and modifications so PIs are encouraged to use this tool.   
  • The PI will be responsible for securing cost estimates/quotes in compliance with sponsor guidelines. Additional guidance is available via BGSU’s Purchasing Policy 3341-6-38, and BGSU’s purchasing best practices.
  • The PI is also responsible for drafting a budget justification that aligns with the budget categories; there is an example Budget Justification (aligned with the BGSU PI Budget Template) available here. The primary purpose of the justification is to explain the need for the requested funding with respect to project-specific objectives and to clearly demonstrate how total amounts were determined. 

Budgets may include institutional commitments or Subrecipients/Vendors/Consultants. Special considerations must be addressed in both cases prior to budget completion.   

  • Institutional Commitments - If there are any institutional commitments, then the Sponsored Programs Coordinator will complete an Institutional Commitment Form with assistance from the PI. The PI will generate brief explanations/justifications to be included with the form and should undertake preliminary discussions with the units involved prior to initiating the signatory process for the Institutional Commitment Form. The Sponsored Programs Coordinator will complete the form and forward for signatures. This form must be approved prior to final approval of the internal budget. The signed form (and attachments) will be uploaded to the electronic project file by the Sponsored Programs Coordinator. 
  • Subrecipients/Vendors/Consultants - The involvement of subrecipients within a grant generates additional complexity. In brief, funds flowing through the grant to another entity/individual that is working in support of the grant goals must be (1) categorized, (2) supported by appropriate documentation, and (3) vetted. Documentation and vetting can vary depending upon how the entity/individual is categorized. Note: categorization is based on the role, not on the budget line.  

Budget Review 

The Sponsored Programs Coordinator will review budgets and budget justifications to verify calculations and suitability, noting that some budget requests may require project-specific justification or be explicitly prohibited by a solicitation or sponsor.   

  • The Sponsored Programs Coordinator will work with the PI to track and review suggested budget or budget justification modifications (e.g. shared documents, tracking).   
  • After the final budget and budget justification are reviewed, the Sponsored Programs Coordinator will upload the documents to the electronic project file and a confirmation email will be sent to the PI.   

Budget Changes 

If internal approvals have been completed and budget revisions arise, contact your Sponsored Programs Coordinator.

Updated: 11/03/2025 11:18AM