Wooster Street update for the week of April 26
Work on East Wooster Street will continue between the Interstate 75 interchange
and the CSX Railroad tracks the week of April 26. Also, work has begun on Mercer
Road between East Poe Road and East Wooster Street. The contractor will be working
Monday-Thursday (April 26-29) this week.
Construction on East Wooster Street
Utility crossover work will continue the length of East Wooster Street. This work
will cause traffic delays and lane closures controlled by flaggers in many areas.
Delays are expected. Local traffic is encouraged to avoid the area if possible.
The city electric department will be relocating telephone poles on the north side
of East Wooster Street from Mercer Road to I-75.
Construction on Mercer Road
The contractor has begun installing a new storm sewer along Mercer Road from East
Poe Road to East Wooster Street. The installation is on the west side of the road.
It will take about four weeks for this work to be completed. As the installation
progresses, updates will be provided to the University community
As was done on East Wooster Street, the contractor is doing pre-trenching of the
rock to speed the installation of the sewer line. Currently the schedule for this
pre-trenching is:
• Monday, April 26—Trenching from north of Ridge Street into the parking
lot east of Kreischer Quadrangle. The lot will be closed to parking Sunday evening
(April 25).
• Tuesday, April 27—Trenching across the rest of the Kreischer parking
lot.
To accommodate this schedule, Ridge Street will be closed all day Monday (April
26) beginning at about 8 a.m. The parking lot east of Kreischer will be closed
from Sunday night (April 25) until roughly 7 p.m. Tuesday (April 27).
All construction schedules are subject to change due to weather and construction-related
issues.
Be alert to increased pedestrian traffic and to the movement of construction vehicles.
Please drive slowly and carefully through all construction zones. The speed limit
on University drives and in all campus parking lots is 15 mph.
Weather permitting, the project will be completed in August 2005. As the contractor
provides updated information, it will be sent to the University community by broadcast
email. Updates also appear in the Monitor at www.bgsu.edu/offices/mc/monitor and
at www.bgsu.edu/offices/mc/wooster.
|