Update - November 2005

PeopleSoft Financial Management Solutions (FMS) Update

The BG@100 Project Office continues to conduct Fit/Gap for FMS during the month of November. Fit/Gap is the process of comparing the BGSU financial business processes with the functionality in the FMS application. This is done to determine where the business processes need to be changed to match the FMS functionality or where additional functionality might be required. Individuals from the Treasurer's Office, Business Office, Bursar's Office, Internal Auditing Office, Capital Planning Office, Office of the Executive Vice President, Office of Finance and Administration, BG@100 Project Office, and other offices have been invited to assist with Fit/Gap. The following is the updated Fit/Gap schedule.

  FMS  Fit/Gap Sessions

 Date

 Topic

 October 4 - October 6  General Ledger / Commitment Control
 October 11 - October 12  Asset Management
 October 18 - October 19  Budgets and Planning
 November 1 - November 3  Purchasing
 November 7 - November 10  Accounts Payable / Grants Management

 

The BG@100 Project team has been engaged in gathering information regarding the many interface systems that generate input to the University's financial system. The team is researching the potential alternatives for accommodating these requirements within the PeopleSoft FMS system. Due to the complexities identified in the current interface processes, it is expected that a substantial effort will be required to engineer a set of solutions that will meet the University's interface needs. The Project Office thanks April Shumaker and Sylvia Cuthbert from the Bursar's Office for sharing information regarding their interaction with the financial system.

The BG@100 Project team is in the initial discovery stage of the data conversion process. They have started identifying the key FMS tables that will require data conversion and have begun the initial steps required to design the Chart of Accounts.

PeopleSoft Human Capital Management (HCM) Update 

The HCM Support Team is assessing the effort required to upgrade the HCM module from version 8.8 to 8.9. The upgrade will likely occur in the first half of the 2006 calendar year. The Support Team is also assessing the effort required to implement eBenefts and eRecruitment.

Return to BG@100 Project Home Page

 