Telephone Deployment Schedule

 

As a part of the Unified Communications (UC) project, TS will be completing a phased cutover to the new Cisco phone system in June and July.  On the date specified below, the phones in the identified buildings will be cutover to the new system.  

In anticipation of each cutover date, new Cisco phones will appear on the desks in each of these buildings.  Please see the UC Telephone-Phase 4 web page for more details about the project.

 

Cutover DateBuildings to be part of Cutover
Thursday, May 30

400 East Poe
Biology Greenhouse
College Park
Central Services Auxiliary
Facilities
Harshman E
Technology Annex
Technology
Warehouse

Wednesday, June 5South
Moseley
Hayes
Huntington
University Hall
Hanna
Wednesday, June 12Field House
Golf
Ice Arena
Rec Center
Sebo
Stadium
Stadium East
Stroh
Visitors Center
Wednesday, June 17Firelands Cedar Point
Firelands Foundation Hall
Firelands North
Firelands West
Wednesday, June 26Chemical Storage
Life Science
Oaks Dining
Overman
Physical Science
Psychology
Wednesday, July 3Business Administration
East
Memorial
Jerome Library
Carillon Dining
Wednesday, July 10Centrex
Education
Eppler Center
Eppler North
Eppler South
Math Science
Olscamp
Wednesday, July 17708 W. Wooster (IR)
Administration
Family & Consumer Science
McFall
West
WBGU
Wednesday, July 24Johnston
Shatzel
Union
Williams
Wednesday, July 31Conklin North
Health
Fine Arts Center
Moore Musical Arts
Wolfe Center